MORE completes repair works ahead of schedule

MORE Electric and Power Corp said it finished the comprehensive preventive maintenance of the Jaro Substation in Iloilo City ahead of schedule on Sunday. (Photo by Leo Solinap)

Iloilo City consumers of MORE Electric and Power Corporation (MORE Power) lauded the power firm’s successful comprehensive preventive maintenance of the Jaro Substation on Sunday, May 17.

The maintenance works were done an hour early than the expected 13-hour long task.

The scheduled power interruption started at 4:00 in the morning and ended at 3:43 in the afternoon.

MORE Power has earlier explained the need to do comprehensive maintenance works of the Jaro Substation as the load of the substation’s 10MVA transformer was found to be already on critical level.

Several netizens have posted their acknowledgment of MORE Power’s prompt maintenance service.

Facebook user Bien Anatan said. “Thank you for a job well done and MORE Power to the Ilonggos. God bless to everyone including those who are forever oppose and are everlasting critique of MORE Power. May MORE Power continue to provide you with excellent service to shut your mouth.”

On the other hand, Jennie Pardilla expressed, “earlier than expected. Kudos!”

Meanwhile, Jazy Borja said, “Good job MORE. Continue the excellent service.” “Dasig! I thought

it’ll be at 5 pm that they will restore the power connection here in Sambag, Jaro. Pero 3.45 pa

lang nagbalik na!”

MORE Power noted that the previous distribution utility, Panay Electric Company, Inc. (PECO), did not conduct any preventive maintenance works on the substation for almost 8 years. According to MORE Power’s technical experts, preventive maintenance should have been conducted every two years.

Unfortunately, PECO neglected to do maintenance and upgrading works which resulted in dilapidated facilities that MORE Power inherited.

Thus, MORE Power took the task of fixing and upgrading all of the former distribution utility’s obsolete, broken, aging, and unmaintained facilities.

Following continuous assessment and inspection, MORE Power has now a benchmark of the expected lifespan of the facilities and has prepared the upgrading of their capacities.

In the past two months that MORE Power came into operation as Iloilo City’s legitimate power firm, it has already made significant improvements and repairs on the metropolis’ electric distribution facilities.

From February 29, 2020 until April 29, 2020, MORE Power has, among its other accomplishments, upgraded 51 distribution transformers, replaced 51 broken electric poles and fixed 97 hotspot connectors, all these in a span of only two months.